I wanted to let you know that the new Bay County International Airport is progressing along very quickly. Approximately 80% of the contract work is complete in only 55.8% of the contact time used on the heavy civil and airfield lighting. The terminal building and support buildings are about 18% complete with 25% of the contract time used. The utilities are complete by about 18% with only about 15% of the time used.
Here is a photo of the terminal building:
Have a great day!
Dana